Previous Page  32 / 76 Next Page
Information
Show Menu
Previous Page 32 / 76 Next Page
Page Background

July

2020

HYDROCARBON

ENGINEERING

30

flexible and reactive service that will keep downtime to a

minimum.

Rotor repairs using weld build-up or high velocity oxygen

fuel (HVOF) coating systems and precision machine tools to

deliver exact tolerances can be achieved as part of proven

and routine repairs. Furthermore, it is possible to restore

rotors that have been damaged and re-establish the outside

diameter (OD) and end strips. This reduces lead times as well

as repair costs and returns the compressor to operational

status at the earliest opportunity.

These tasks require specialist tooling to accomplish, such

as engine lathes with engineered attachments that enable

OD strips to be re-established. This should also be

supported by a test stand that allows both rotors to be

positioned in the ideal running position to verify lobe

clearances. These offer the additional benefit of being able

to check the timing gear runout and backlash, before the

rotors are installed in the casing. These are important

inspections that enable a potential issue to be found before

final assembly of the compressor.

Case study: design upgrades

There are situations where a compressor application has

changed or the original design was not perfectly suited to

the process. In these cases, repair frequency can be higher

than anticipated, leading to increased downtime. The

solution can often lie in an improvement of the OEM design.

This is exemplified by a facility whose process was

causing erosion and corrosion to the rotor bores and the end

walls, to the point that the OEM recommended replacing

the case during each overhaul. The compressor in question

was a large 25 in. (635 mm), horizontally-split screw

compressor, manufactured using carbon steel.

Expert evaluation of the compressor was conducted with

a view to extend the operational life of the casing, but this

concluded that the case material was inadequate for the

application. The first solution would be to replace the

material with 316L stainless steel, but the cost was

prohibitive.

The alternative, cost-effective solution was to machine

the rotor bores and the end walls to allow a 309L inlay pass

to be applied as well as 316L top layer cladding. The split line

was seal welded and the inner surfaces machined to ensure

that all the original internal fits and clearances were correct.

This proved to be the ideal solution for the operator, who

ordered the same rework on a second compressor and has

now doubled the mean time between failure (MTBF).

Case study: improving pipeline

application

In another example, a large screw compressor that had been

recently installed on a new pipeline did not always operate

at full capacity continuously. The varying needs of the

pipeline meant that there were frequent starts and stops as

well as changes in capacity requirements.

After a very short initial run, the compressor failed and

the standby unit had to be installed while the original unit

was transported to a maintenance centre. However, soon

after the compressor arrived, the replacement unit failed as

well, apparently with the same failure mode.

The initial inspection showed that the slide valve had

come into contact with the OD of the rotor. A thorough

review found that the slide valve shaft was long enough to

deflect once the valve was fully opened. The amount of

deflection was sufficient to allow the slide valve to lift at a

slight angle and this was just enough to place it in contact

with the rotor. This caused the rotor to become unstable

and vibrate to the point of shut down.

To address this condition, the slide valve shaft was

stabilised by adding supports, which acted as a bearing. The

modification was installed on both units and since then they

have been running for over five years with no further issues.

Boosting reliability

The objective of every business that operates expensive

assets is to optimise their availability and productivity. In

most cases, these pieces of equipment are part of a much

larger process, but if one of them fails, the knock-on effects

can be substantial. The majority of downtime costs are

associated with lost production, rather than the cost of the

repair, so speed is of the essence.

At the heart of every successful maintenance routine is

prevention. Regular inspections, constant monitoring and

immediate action when warning signals are raised, are the

best courses of action. However, a failure can occur

unexpectedly and it is the action that is taken here that can

have a significant impact on the business.

Maintenance partners can offer specialist advice and

expertise, as well as a responsive and flexible approach to

repairs. Most OEMs are limited to their own products,

whereas independent suppliers have a much wider

experience of designs and solutions. They also have greater

resources aimed specifically at repairs and the refurbishment

of legacy equipment, rather than simply replacing

components.

Ultimately, the aim is to deliver the most cost-effective

solution to a problem. The key is establishing a range of

solutions so that the equipment owner can make a

well-informed decision, based on the needs of the business.

In many cases, that will be the fastest delivery, while

improved durability in the long-term can deliver ongoing

benefits for the future.

Figure 3.

Damage occurred to the widow’s peak due

to an overheating event.