Previous Page  44 / 100 Next Page
Information
Show Menu
Previous Page 44 / 100 Next Page
Page Background

August

2019

HYDROCARBON

ENGINEERING

42

ethylene purity and recovery suffered. It was clear that both

the capacity and efficiency of the trays were limiting the

operating rates of this plant. The engineering company/licensor

considered several alternatives, including trays with a large

number of downcomers at a lower tray spacing. Due to the

lower efficiency of such trays, the number of trays would have

had to be increased by 23%.

4

The trays would have had to

exhibit an increased capacity that would overcome a

23% reduction in tray spacing and give the customer the extra

24% capacity it was targeting. The amount of work needed to

reduce the trays spacing would also have raised hot work issues

and would have extended the shutdown.

The owner of the plant decided to use optimised

SUPERFRAC trays for this revamp. The number of trays and tray

spacing in the different zones of the tower were adjusted to

achieve the maximum capacity and recovery given the purity

constraints. This study showed that a one-for-one tray

replacement with optimised trays would meet the objectives.

Changes in downcomer arrangements could be

accommodated using the OMNI-FIT technology. This approach

removed the need for welding and significantly reduced the

duration of the shutdown. In addition to the tray features

discussed in case study 2, this revamp configuration also

optimised the feed arrangement, reboiler return, side reboiler

draw, and return and reflux distribution. Based on Koch-Glitsch

calculations, the new tower arrangement would increase the

ethylene production to 25% above the target set by the

operating company. At that point the capacity would be

limited by the reboilers, condenser and the pumps, and not the

trays.

The tray installation and piping modifications were

successfully completed within the allotted turnaround time.

The tower was then started up without any issues and the

product purity and recovery was reached quickly. Test runs

were conducted to assess the separation performance and

capacity of the revamped tower. At 96% of the desired rate,

the upstream units reached their maximum capacity and it was

not possible to push the tower to its limit. Even with the

limitation of the upstream units the plant was able to increase

its ethylene production capacity by 26%. Over the whole

operating range of the tests, the overall tray efficiency was

higher than 96%.

Case study 4 – a new C3 splitter in a

grassroots PDH plant

An even larger propane/propylene splitter has been in service

for over two years with the first ever 8-pass SUPERFRAC XT

trays.

5

The 33.5 ft (10.2 m) dia. column has exceeded design

capacity and product purity requirements from the initial

start-up.

This grassroots PDH plant has a capacity that called for one

of the largest C3 splitters in the world at just over 10 m in dia.

and over 100 m tall. The plant owner selected SUPERFRAC XT

trays based on criteria including proven performance, minimum

tower size and ease of accessibility. Minimising the pressure

drop was also an important factor since the splitter has a heat

pumped reboiler driven by the compressed overhead vapours.

The reliably high tray efficiency allowed fewer trays to be

specified, resulting in a shorter vessel height, and lower

pressure drop, requiring less compressor horsepower.

Koch-Glitsch worked closely with the owner’s subject

matter experts and their chosen engineering contractor to

define the scope of the splitter tower internals. An 8-pass

SUPERFRAC XT tray design with several of the features discussed

above was selected for this application. With this being a new

tower, the tray design, tower diameter and tray spacing could be

optimised. Sectionalised beams were used to support the tray

decks, with tray levelness being an important factor to ensure

that the maximum performance would be achieved.

To minimise fit up errors, OMNI-FIT technology was used

to significantly simplify the design of the supporting tower

attachments that had to be welded inside the tower by the

vessel fabricator. This provided greater flexibility to the tray

installer to ensure an accurate installation was achieved. Even

with the much-simplified tower attachment scope, several

deficiencies in the fabrication of the tower had to be

overcome during the installation.

On all towers the support rings must be levelled within a

manufacturer-specified tolerance. The support ring level should

be checked at the vessel shop before customer acceptance. A

final check of the support rings should be made prior to

beginning installation of the trays. If any of the rings exceed the

specified tolerance for level, the tray manufacturer should be

contacted immediately to agree upon a plan for rectification. For

the PDH splitter, Koch-Glitsch sent a Certified Tower Specialist

to the site to verify the tray installation, and he and the project

teamworked with the tray installers to ensure a quality

outcome.

The PDH unit started up in November 2015 and by

February 2016, it was running at full capacity, delivering

polymer-grade quality propylene from the initial startup

without any issues. The tower is meeting all capacity, purity

and recovery expectations. The overall tray efficiency is above

90%, which is higher than what the engineering company

assumed during the design phase. This allows the owners to

adjust the reflux ratio to optimise the production and minimise

the energy consumption.

Conclusions

The case studies presented in this article show that high tray

efficiencies and capacities can be obtained with optimised

SUPERFRAC XT trays. In C2 and C3 splitters, efficiencies of 92%

to 100% have been obtained. This allows debottlenecking of

existing splitters or a reduction in diameter and height for

grassroots splitters. It also allows the energy consumption of

these mega towers to be minimised. In the case of heat-pump

splitters, the energy consumption and size of the heat-pump

system may also be minimised.

References

1. NIEUWOUDT, I., and SANDFORD, N., ‘Overcoming challenges: part one’,

Hydrocarbon Engineering

, Vol. 24, No. 4, (April 2019), pp. 39 – 42.

2. NIEUWOUDT, I., KARPILOVSKIY O., and LOCKETT, M.J., ‘Revamp

and Retune’,

Hydrocarbon Engineering

, Vol. 14, No. 7, (July 2009),

pp. 56 – 60.

3. NIEUWOUDT, I., ‘Tray efficiency of SUPERFRAC high-performance trays

in C2 splitter service’,

Hydrocarbon Asia

, April-June, (2011),

pp. 64 – 68.

4. SUMMERS, D. R., MCGUIRE, P. J., GRAVES, C. E., HARPER, S. E., and

ANGELINO, S. J., ‘High-Capacity Trays Debottleneck Texas C3 Splitter’,

Oil & Gas Journal

, Vol. 93, No. 45, (November 1995).

5. ‘Dow PDH unit completes performance test’, Dow, https://www.

dow.com/en-us/news/press-releases/dow-pdh-unit-completes-

performance-test