Previous Page  42 / 100 Next Page
Information
Show Menu
Previous Page 42 / 100 Next Page
Page Background

August

2019

HYDROCARBON

ENGINEERING

40

a significantly higher feed rate. Though Koch-Glitsch did not

supply the original equipment, given the history of poor tray

performance in the C3 splitter, an extensive review of the tray

technology to be used in the revamp was made by the plant

engineering staff together with an independent third-party

consultant. The review included a demonstration in

Koch-Glitsch’s 5.5 ft (1.67 m) hydrocarbon pilot plant

distillation tower, which closely reproduced the hydraulic

design conditions for the revamp. Following this review, a

6-pass SUPERFRAC XT tray design was selected. Several of the

features discussed above were included in this design. This

included extensive use of OMNI-FIT technology that allowed

the flow path length and downcomer widths to be changed

without welding to the tower shell. More than 150 existing

4-pass trays were removed and replaced by 6-pass

SUPERFRAC XT trays (Figure 2) plus two dedicated distributor

trays and new feed pipes at the reflux and feed entry points.

The installation work was completed safely and on time. It

only took 38 working days from the initial tower entry to the

completion of the new tray installation. Such a compact

schedule was only possible through a close one-source

solution working relationship between the Koch-Glitsch

equipment design team and the Koch Specialty Plant Services

installation project team. The installation team made several

key inputs during the detailed design phase that helped to

shape the final equipment scope, ensuring it would allow rapid

and safe installation while working on multiple levels in the

tower. During the installation work in the field, the design team

was constantly available to assist with timely resolution of any

issues that arose.

Following the revamp with SUPERFRAC XT trays, the overall

tray efficiency increased from approximately 78% to 94%. The

tower is now meeting the product purity goal at the higher

feed rate. Propylene in the bottom product recycle is less than

50% of the design slippage, allowing the energy consumption

(including heat pump compressor duty) to be optimised by

reducing the reflux ratio. The new trays also have a lower

pressure drop, which further reduces the energy consumption

in the heat pump compressor.

Case study 2 – revamp of a C3 splitter

Due to an increase in the global demand for polymer grade

propylene, the operating company embarked on a programme

to increase its propylene production capacity.

2

It wanted the

maximum possible capacity while maintaining recovery and

purity specifications. The tower was equipped with 4-pass

valve trays. Koch-Glitsch analysed the plant data and

concluded that the trays were limited by jet flood and

downcomer flood limitations. In an un-flooded state, these

4-pass valve trays were giving efficiency values of

approximately 98%.

The operating company evaluated several alternatives

before deciding on revamping the tower with 6-pass

SUPERFRAC trays. The challenge was to get the same or better

tray efficiency with trays that had flow path lengths that were

approximately 33% shorter. To address this, the following

features were used on these trays:

„

Downcomer shapes and sizes that would maximise the

downcomer capacity.

„

Valves and valve arrangements that would maximise the

entrainment flood capacity and efficiency.

„

Features to regulate the froth flow pattern and froth

heights to maximise the tray efficiency. Changes in the

number of downcomers and the downcomer sizes could

be accommodated using the OMNI-FIT technology.

After an initial upset caused by a faulty sump level

transmitter, the tower was started up successfully. Upon

ramping up rates it was found that there was not enough

condenser capacity and feed to push the tower to the

capacity limit of the trays. At a capacity increase of 24%, these

limitations prevented a further rate increase. The propylene

purity and recovery was maintained at these increased rates.

Over the whole operating range of the tests, the overall tray

efficiency of the SUPERFRAC trays was 100%.

Case study 3 – revamp of a C2 splitter

This tower was producing only 76% of the desired ethylene

production rate.

3

When the tower was pushed higher, the

Figure 1.

This 28 ft (8.5 m) dia. x 330 ft (100 m)

tall propane/propylene splitter was retrofitted with

SUPERFRAC

®

XT trays.

Figure 2.

6-pass SUPERFRAC XT trays with

PINNED-TRUSS beams.